Anders Nilsson (andersn), Alexander Pisarevskiy (alexanderp)
Precursors:
M move heavy stuff (milestones.m_tunga_lyft) ]->[ 2023-04-15, Safety System assembly (KC) (robot_lab.safety_kc_assembly) ]->[ 2020-06-02
Followers:
Start: 2023-05-24 End: 2023-05-29
Resources:
Anders Nilsson (andersn), Alexander Pisarevskiy (alexanderp), Anders Blomdell (andersb)
Precursors:
M general access (milestones.m_general_access) ]->[ 2023-05-01, M final move (milestones.m_relocation) ]->[ 2023-05-24, Safety System assembly (KC) (robot_lab.safety_kc_assembly) ]->[ 2020-06-02
Followers:
Start: 2023-01-19 End: 2023-02-15
Resources:
Alexander Pisarevskiy (alexanderp)
Precursors:
Followers:
1
Milestones
ID: milestones
2020-01-01
2023-09-01
1.7
M build start
ID: milestones.m_build_start
2023-01-30
2023-01-30
1.8
M move heavy stuff
ID: milestones.m_tunga_lyft
2023-04-15
2023-04-15
1.9
M general access
ID: milestones.m_general_access
2023-05-01
2023-05-01
1.10
M final move
ID: milestones.m_relocation
2023-05-24
2023-05-24
1.11
Leave KC
ID: milestones.kc_leave
2023-09-01
2023-09-01
2
Robotics Lab
ID: robot_lab
2019-11-18
2023-05-29
2.12
L3
ID: robot_lab.robot_L3
2023-01-23
2023-02-10
2.12.1
Disassemble
ID: robot_lab.robot_L3.disassembly
2023-01-23
2023-01-24
2.12.2
Move
ID: robot_lab.robot_L3.move
2023-01-25
2023-01-25
2.12.3
Reassembly+test
ID: robot_lab.robot_L3.reassembly_test
2023-01-26
2023-01-27
2.12.4
Install safety controller
ID: robot_lab.robot_L3.safety_controller
2023-01-27
2023-02-10
2.13
Safety System (M)
ID: robot_lab.safety_m
2023-01-30
2023-03-21
2.13.1
Design (M)
ID: robot_lab.safety_m.design
2023-01-30
2023-02-08
2.13.2
Procurement (M)
ID: robot_lab.safety_m.procurement
2023-02-08
2023-02-22
2.13.3
Test (M)
ID: robot_lab.safety_m.test
2023-02-22
2023-03-06
2.13.4
Assembly (M)
ID: robot_lab.safety_m.assembly
2023-03-06
2023-03-21
2.14
Robotlab fences
ID: robot_lab.fencing
2023-01-30
2023-04-06
2.14.1
Design
ID: robot_lab.fencing.design
2023-01-30
2023-02-09
2.14.2
Procurement
ID: robot_lab.fencing.procurement
2023-02-09
2023-03-23
2.14.3
3D printed parts
ID: robot_lab.fencing.print_3d
2023-02-09
2023-03-09
2.14.4
Build
ID: robot_lab.fencing.build
2023-03-23
2023-04-06
2.15
Move heavy robots to M
ID: robot_lab.robot_move_heavy_m
2023-04-17
2023-04-21
2.16
Move light robots to M
ID: robot_lab.robot_move_light_m
2023-05-24
2023-05-29
2.17
Organize stuff on shelves
ID: robot_lab.organize_shelves
2023-01-19
2023-02-15
Container Task
Normal Task
Milestone
Off-duty period
Project: Planning (at KC) Version: 1.0 - Created on 2025-10-09 10:43:29 with TaskJuggler v3.8.1